Project
Summary: Folsom Dore Apartments
OWNER
Folsom/Dore Associates, a CA Limited Partnership
DEVELOPER
Citizens Housing Corporation
ARCHITECT
David Baker + Partners, Architects
ASSOCIATE ARCHITECT
Baker Vilar Architects
LANDSCAPE
ARCHITECT
Andrea Cochran Landscape Architects
CONTRACTORS
Cahill Construction, Inc.
PROPERTY MANAGEMENT
CHC Property Management Company
FUNDERS: |
TYPE: |
City of San Francisco |
HOME funds |
Apollo Housing Capital |
4% LIHTC |
Citibank |
Tax Exempt Bonds |
Federal Home Loan Bank |
Affordable Housing Program Funds |
State of California |
MultiFamily Housing Programn |
Pacific Gas and Electric |
Multifaily Comfort Home Program |
California Energy Commission |
Solar Rebate |
DEVELOPMENT
TYPE:
New construction studio, one and two bedroom rental apartments.
RESIDENT
PROFILE:
Low-income, 25% and 60% AMI, and special needs including
physical or developmental disabilities, chronic homelessness,
chronic unemployment, and HIV/AIDS illness.
DENSITY:169 units per acre
DEVELOPMENT
PROFILE
Type |
#/Units |
Size
(sf) |
Rent |
Studio |
33 |
500 - 596 |
$438 - $1038 |
1 BR |
57 |
520 - 69 0 |
$469 - $1272. |
2 BR |
8 |
780 |
$562 - $1526 |
Total |
98 |
|
|
Laundry: Community laundry
Courtyard/play: Commong courtyard with playground
Parking: 30 garage spaces, 4 for are a City Car Share pod); 28 bicycle spaces
Total site area:
25,2952sf (.58 acres) |
CONSTRUCTION
TYPE
Wood frame above masonry.
DEVELOPMENT
COSTS:
Land cost: $5,700,000; Constr. costs:
$14,400,000; Other costs: $6,900,000; Total
development costs: $26,500,000 ($270,408/unit);
Completed in February 2005.
|
|
|
Folsom Dore - San Francisco, CA
Green Features
Citizens Housing Corporation (CHC) worked with the
City of San Francisco to build Folsom Dore Apartments, 98 units of affordable
housing for low- and very low-income residents with a variety of special needs.
Folsom Dore promotes an active social environment for its residents through the
integration of interior community and service space, where residents have access
to social service case management, a computer learning center, and a wide range
of youth and adult education and support service programs.
Folsom Dore’s design deftly responds
to and interacts with the surrounding mixed-use urban nature of its South of Market
(SOMA) neighborhood in San Francisco. A portion of the brick warehouse that was
demolished to build Folsom Dore was kept intact and incorporated into the building’s
front elevation. The brick façade marks the project’s community meeting room, giving
it a strong street presence and illustrating the priority given to resident interaction.
Enveloping the existing façade, the project’s new construction speaks to the evolving
nature of the neighborhood through its modern aesthetic and variety of colors and textures.
Other unique design features include an entry garden court and green stair, which provide
residents with a transitional space between the hard urban exterior environment and the
inviting dwellings within. In addition, the development creates a new pedestrian-friendly
street edge on a previously blighted alley using plantings at the property line, street
trees along the sidewalk and protective pipe bollards.
As part of their fully integrated design process, CHC brought the general contractor
onto the project team at the end of schematic design. In addition, a sustainable
design consultant guided the project team from start to finish. Other members of the
team included the architect, and engineers. The design was also guided by input from
local residents and business owners. The owner’s property management team provided
input based on post occupancy evaluations from their existing buildings. CHC worked
closely with neighboring businesses and the San Francisco Chamber of Commerce to develop
a parking plan and construction staging schedule that would accommodate the project’s
needs with a minimal impact on area businesses.
Folsom Dore is
a high-density development that was built on a 0.58 acre underutilized infill site
replacing a warehouse and a surface parking lot. Its
brownfield site required environmental remediation. As part of a transit-oriented
design strategy, parking was decreased by 70% (30 spaces for 98 units). City CarShare
- a service where residents and community members can rent fuel-efficient vehicles as
needed - has access to 4 parking spaces, and onsite secure bicycle parking is provided
for over 15% of the units. Furthermore, the project is located within one block of
multiple major bus transit lines and within 3 blocks of a regional subway system.
To ensure longevity and minimize
long-term maintenance needs, the development utilizes a variety of durable materials
and systems without sacrificing quality design. These include: a concrete base along
the main ground floor exterior; commercial-grade windows throughout; ground and polished
concrete flooring in the community space and first floor residential hallway; exterior
stucco; a steel and concrete main residential staircase; and fluorescent lighting within
the units and common spaces.
Folsom Dore’s heat and hot water is
provided by a highly efficient hydronic system. Through operable windows and passive
exterior ducts, natural ventilation is provided to all units, eliminating the need for
air conditioning in the apartments. The project’s pitched roofs are oriented and sloped
to maximize solar exposure for the 13 KW photovoltaic system that provides energy for
common space lighting. To keep electric loads down, seventy-five percent of all lights
are fluorescent and the majority of common spaces have occupancy sensors. In addition,
all units are equipped with Energy Star Appliances.
These strategies and other energy-saving measures make the building 20% more efficient
than State code requirements.
The development incorporates many recycled
materials and includes: Robertson Industries TotTurf (recycled tire play lot surface),
recycled paper gypsum board, recycled-content Diamond Bond Carpet pad, recycled-content
carpet in units, Lonseal sheet vinyl in bathrooms (containing 40% recycled materials),
recycled-content sheet vinyl in corridors (30% recycled content), recycled-content MDF
trim, wheat board cabinet doors and drawers and high fly-ash content concrete. In addition,
the contractor reduced at least 70% of the construction and demolition waste. On-site tenant
recycling collection is located in the trash room on each residential floor. For improved
indoor air quality, urea-formaldehyde free cabinets, and low- and no-VOC paints and sealants
were used as well as natural linoleum flooring in select unit interiors. Also, using exhaust
fans, bathroom and kitchen exhaust and moisture are drawn directly outside the building via
mold-resistant lined ducts.
To minimize water-use yet still provide green
space in a dense urban environment, the rear courtyard features a combination of limited
at-grade plantings and water-efficient plantings in pots with a bubbler irrigation system.
In addition, per California standards, the project uses low flow showerhead and toilets.
Lessons Learned from
the architect
- Incorporating new products and strategies into the drawing set and specifications is fairly
simple, but ensuring that what is in the construction documents is what gets built takes a lot
more diligence for a green building. Folsom Dore was built as we intended, in large part because
we had an on-site project engineer who was LEED accredited, was there every day and was
personally committed to the project.
Beware of substitutions when reviewing submittals.
We specified an insulation product with no urea formaldehyde binders. However, a product with low
urea formaldehyde was submitted and it got past us. In that instance, its incorporation made a
relatively small difference to the overall indoor air quality because residents are not in direct
contact with the insulation. On the other hand, if a wrong paint product had been approved, it
could have had a big impact on the indoor air quality of the project.
Lessons Learned from the developer
- Select a Good Project Team: It is critical that both the Contractor and the Architect are familiar
with and willing to participate fully in a sustainable and green building design and construction.
Their cooperation is integral to ensure that appropriate design and implementation of the sustainable
aspects of the project are completed.
Establish Goals: Establishing sustainability and Green
Building goals at the beginning of a project, even if they are very general, helps the entire project
team understand the owner and design team’s interest in integrating Green Building practices into the
project site and buildings.
Carry Alternates: As affordable housing developers, we
are often faced with budget constraints. Therefore, it may not be possible to incorporate all sustainable
and green features in the total project budget from day one. However, if the architect includes sustainable
alternates in the specification set and the owner has the contractor price the alternates throughout the
pricing phases, the team will have accurate, up-to-date pricing on the "Green" alternates. This information
can be helpful in evaluating the feasibility of incorporating particular alternates as the project financing
structure progresses.
Evaluate Green Building Measures: Because it may not
always be financially feasible to integrate all potential Green Building measures in each project, it
is important to evaluate which measures are appropriate for a given project.. Furthermore, all Green
Building measures may not be suitable for all project types. However, a good rule of thumb is to evaluate
sustainable and Green Building features on their ability to maximize the durability and longevity of the
building and the site features as well as reduce long term maintenance and operation costs. Taken together,
these factors often help justify the higher upfront capital costs. Most importantly, Green Building
features will improve the livability of the housing environment and the quality of life for the residents.
Ongoing Education: Green building and sustainable
practices do not end when the building is complete. Ongoing education for residents and maintenance
staff is critical to ensure that the benefits of the green building are maximized. This ongoing education
includes operations and maintenance training for building staff as well as formal and informal educational
programs for residents to demonstrate the importance of many of the green building features. It is very
important that the design and development team sufficiently transfer knowledge to the management team and
that the management team is supporting the sustainability and green building goals.
Click here to see the AIA Affordable Green Guidelines
Green Features
|
Folsom Dore Apartments
|
Use of Brownfield |
.58 acre infill brownfield site required environmental remediation. There was an existing warehouse and a surface parking lot on the site. |
Access to Public Transportation |
The project is located within one block of multiple major bus transit lines and within 3 blocks of a regional subway system.
|
Compact Development |
The project density it 196 units per acre.
|
Passive Heating and/or Cooling |
Through operable windows and passive exterior ducts, natural ventilation is provided to all units, eliminating the need for air conditioning in the apartments. |
Daylighting |
All units have windows placed for deep daylight penetration. Studios have double high spaces with high windows and skylights. |
Superinsulation |
Exterior walls are R-21, roofs trusses are insulated to R-38. |
High Performance Windows |
High-performance thermally-broken commercial grade aluminum windows. |
Energy Efficiency Heating and Cooling |
Folsom Dore’s heat and hot water is provided by a highly e is provided by passive ventilation efficient hydronic system. All cooling |
Energy Star Appliances/Lighting |
All units are equipped with Energy Star Appliances. |
Renewable Energy |
The project’s pitched roofs are oriented and sloped to maximize solar exposure for the 13 KW photovoltaic system that provides energy for common space lighting. |
Water Efficient Landscaping |
The rear courtyard features a combination of limited at-grade plantings and water-efficient plantings in pots with a bubbler irrigation system. |
Water Saving Appliances |
Per California standards, the project uses low flow showerhead and toilets.
|
Local Materials |
Over 40 project materials were local, including: TotTurf by Robertson Industries, wood roof trusses, metal studs, gypsum wallboard, wood doors, cast-in-place concrete mix, rebar and Arcadia Glazed Systems/ Entrance doors. |
Recycled Content Materials |
Robertson Industries TotTurf (recycled tire play lot surface), recycled paper gypsum board, recycled-content Diamond Bond Carpet pad, recycled-content carpet in units, Lonseal sheet vinyl in bathrooms (containing 40% recycled materials), recycled-content sheet vinyl in corridors (30% recycled content), recycled-content MDF trim, wheat board cabinet doors and drawers and high fly-ash content concrete. |
Low VOC Materials |
Urea-formaldehyde free cabinets, and low- and no-VOC paints and sealants were used as well as natural linoleum flooring in select unit interiors. |
Other Innovations |
As part of a transit-oriented design strategy, parking was decreased by 70% (30 spaces for 98 units). City CarShare - a service where residents and community members can rent fuel-efficient vehicles as needed - has access to 4 parking spaces.
|
|