Standard Cost Variance Calculations and Analysis |
Cost of producing
product or service is the total of uni
This data
should cause appropriate corrective action to be taken.
|
Material Price | Tells how much more than budgeted (standard) price was paid (or
less) for the material that was used or bought |
Material Usage | Tells whether the quantity of material used is more than what
should have been used according to the standard and what the $ value is |
Labor Price | Tells how much more or less was paid to workers per hour than
the standard set and what the $ value is |
Labor Efficiency | Tells difference between the hours expended and paid for
compared to what should have been if standard was met |
Overhead Budget Variance | Difference between the actual OH cost spent and what should have
been spent if budget was met |
Oh Efficiency Variance | Difference of what should have been spent if budget was
met and what actual production should have cost if standards were met |
OH Volume Variance | Difference due to output volume change from that planned which
caused less or more fixed OH to be applied |
Re Cap - Variances may be due to:
Reasons for this are numerous and must
Analysis of Overhead Variance = Budget (Spending) Variance Actual Overhead Incurred Flexible Budget Allowance for Actual Operating Level Efficiency Variance Flexible Budget Allowance For Actual Operating Level Flexible Budget Allowance For Actual Units Produced
Capacity Variance
|
Capacity
Variance Standard Cost and OH Variance Analysis Example The Standard Cost
for a product is: |
Direct Material | 2 lbs. @ $l5 per lb. | $30 |
Direct Labor | 2 hrs. @ $20 per hr. | 40 |
Variable OH | 2 hrs. @ $5 | 10 |
Fixed OH | 2 hrs. @ $8 | 16 |
Total Unit Cost | $96 |
Anticipated production is 7,500 direct labor hours. Fixed OH budgeted to be $60,000. Actual Output 6,000 Standard Labor Hours (3,000 units) Actual Variance OH Expense $30,600 Actual Fixed OH Expense $62,000 Bought and used 12,000 lbs. @ $17 lb. $204,000 Paid for 6,500 hrs. of Direct Labor $13,000 D.M. Price Variance
(17-15) 12,000 = 24,000 UNF D.M. Usage Variance (12,000-12,000)(15) =
0 D.L. Price Variance (21-20)(6,500) =
6,500 UNF D.L. Efficiency Variance (6,500-3,000(2))(20) =10,000 UNF Fixed OH Flexible Budget Variance
Actual Cost - Budget based on standard inputs allowing for actual outputs achieved
62,000 -
60,000
= 2,000 UNF (Fixed irrespective Fixed OH Production
Volume Variance Budgeted Cost -
Fixed OH Applied 6,000
6,000(8) =
12,000 U
Variable OH Flexible
Budget Variance Actual
V OH Cost - Budget Based on Standard
30,600
6,000(5) = 600 U Variable OH
Applied
Budget
Applied
6,000(5)
6,000(5) = 0 Analysis - OH Spent $92,600 - Should have if within budget 6,000(8+5) = $78,000
14,600 U Because worked at 6,000 instead of 7,500, did not absorb the
Fixed OH fully. Fixed 60,000 (Budget) - 6,000(8)
= 12,000 not
absorbed 62,000 Actual - 60,000
(Budget) 2,000 spent more than budget 30,000 should have spent if - 6,000(5)
- V.OH =
-0-
standard was met
applied
TOTAL = 14,600 |